BUSI 411 Homework 14 JIT and Lean Operations Assignment solutions complete answers

BUSI 411 Homework 14 JIT and Lean Operations Assignment solutions complete answers

BUSI 411 Homework 14 JIT and Lean Operations Assignment solutions complete answers

 

Compute the takt time for a system where the total time per shift is 380 minutes, there is one shift, and workers are given 2 13-minute breaks and 30 minutes for lunch. Daily demand is 354 units. (Round your answer to 2 decimal places.)

 

What cycle time would match capacity and demand if demand is 160 units a day, there are 1 shift(s) of 445 minutes each, and workers are given two 30 minute breaks during each shift, one of which is for lunch or dinner? (Round your answer to 2 decimal places.)

 